ADP Projects have a core group of qualified technical staff, supported by financial and administrative personnel and technical associates where required. Technical skills available include:
- Senior Project Managers with relevant minerals experience
- Multi-disciplinary engineering
- AutoCAD draughting and 3D Design
- Construction management
- Commissioning
E-Bay Final RecoveryNamdeb2003 / 2004 The Elizabeth Bay Final Recovery, built in 2004 is a 1,4 tonne per hour diamond final recovery plant using De Beers "CDX" and "XST" dry X-Ray technology and "Raven" single particle sorting, contained in a purposed-built steel frame brick... |
|
E-Bay Front End UpgradeNamdeb2006 The Elizabeth Bay Front-End upgrade was designed and implemented for Namdeb's Elizabeth Bay mine in Luderitz, Namibia in 2006... |
|
OrbitNamdeb2005 This project- acronym "Optimum Recovery By Innovative Technology" consisted of the supply of an X-ray re-concentration plant with 2 high capacity UltraSort DP-6 X-ray machines and a UltraSort JS-12 unit together with a 165 tonne per hour... |
|
Orapa Test Recovery PlantDebswana2007/2008 The Orapa Test Recovery Plant comprised the design and build of a diamond recovery facility aimed at testing various X-Ray technologies as well as a grease recovery system for the proposed new Orapa 3 diamond recovery plant... |
|
Geological Sampling Recovery PlantNamdeb2006/2007 The Geological Sampling Plant at Namdeb in Namibia is a purpose built steel-frame brick recovery plant aimed at batch treating concentrates from various sources with a high degree of accuracy, using De Beers ModRup wet X-Ray machines... |
|
Orapa 3 Final Recovery Plant StudyDebswana2008/2009 Fluor-Daniel Australia commissioned ADP to design the Orapa 3 Final Recovery Plant as input to the overall feasibility study for the proposed new Orapa-3 project for Debswana. The design is aimed at recovering diamonds from a DMS... |
|
Floating Treatment PlantNamdeb2007/2008 Fire damage in 2005 resulted in severe damage to the Floating Treatment Plant at Namdeb's Mining Area No.1 and production was ceased. |
|
LogwasherDebswana2008/2009 Debswana commissioned ADP to design, fabricate, construct and commission a Logwasher facility to treat the Main Treatment Plant Tailings prior to the Recrush Plant. The material has a high clay content and is problematic to treat... |
|
Modular Tailings Treatment PlantDebswana2009/2010 ADP has been commissioned by Debswana to design a Rapid Deployment Plant (Capacity 400 tph), to treat dump tailings at the Jwaneng Mine in Botswana, for Debswana. The rapid deployment principle enables a plant to start producing... |
|
![]() |
Morupule CollieryDebswana2009/2010 The Morupule Colliery Limited (MCL) is a coal mining operation that is 100% owned by Debswana Diamond Company. Debswana in turn is a 50/50 joint venture between De Beers and the Botswana Government. The Colliery has been in.. |